R
RChrisR
I have a master project with many inserted projects. I have another
file which contains the Resource Pool. I am using MS Project 2003. I
am using a split view with Resource Usage on top and Resource Graph on
the bottom.
I want to be able to see the correct results in the Resource Graph for
a particular resource across the projects. Within the Resource Usage, I
am grouping by "Assignments Keeping Outline Structure". The grouping
seems to be fine and the roll-up of all the various hours on all the
various projects is correct. However, I can't figure out how to get the
Resource Graph to show the correct allocations.
1) I have selected the roll-up line for the specific resource in
Resource Usage and I get 0 allocations in the resource graph (0 for any
of the months that have usage of the resource).
2) If I select one of the tasks under the resource grouping in
Resource Usage, I do get the correct graph for that line, but that
doesn't solve my question for seeing the graph for all the tasks
assigned to that resource.
3) If I select multiple tasks (or all tasks) under the specific
resource in resource usage view I get a graph that shows data but it
doesn't match the roll-up total for the resource.
How can I get the Resource Graph to show the correct resource usage
totals for a specific resource?
http://forums.techarena.in/microsoft-project/1037259.htm
file which contains the Resource Pool. I am using MS Project 2003. I
am using a split view with Resource Usage on top and Resource Graph on
the bottom.
I want to be able to see the correct results in the Resource Graph for
a particular resource across the projects. Within the Resource Usage, I
am grouping by "Assignments Keeping Outline Structure". The grouping
seems to be fine and the roll-up of all the various hours on all the
various projects is correct. However, I can't figure out how to get the
Resource Graph to show the correct allocations.
1) I have selected the roll-up line for the specific resource in
Resource Usage and I get 0 allocations in the resource graph (0 for any
of the months that have usage of the resource).
2) If I select one of the tasks under the resource grouping in
Resource Usage, I do get the correct graph for that line, but that
doesn't solve my question for seeing the graph for all the tasks
assigned to that resource.
3) If I select multiple tasks (or all tasks) under the specific
resource in resource usage view I get a graph that shows data but it
doesn't match the roll-up total for the resource.
How can I get the Resource Graph to show the correct resource usage
totals for a specific resource?
http://forums.techarena.in/microsoft-project/1037259.htm