I have multiple projects; I have designated an enterprise flag field to
identify key tasks. I created a view to show only those tasks with Yes in the
flag field. I want tp create a Master project so I when I look at the Key
task view I created, I will see all key tasks from all Projects. THere are
two check boxes in Server Configuration, one to allow 'saving" master
projects, and one to allow "publishing" master projects. What will be the
effects of one or the other?
 
D

Dale Howard [MVP]

Vig --

You can safely set the Server configuration option to save master projects,
but do not allow users to publish master projects. If you allow the
publishing of master projects to the Project Server database, it will cause
double assignments for all resources in subprojects of the master project.
Hope this helps.
 