I have created a template to use for creating individual similar
projects. I have also created a shared resource pool. Becuase the
individual projects are similar and I am using a template, a lot of
the task names remain the same across projects. The difficulty arises
when trying to join the individual projects into a master project.
When looking at the various views, tables, etc, for example resource
usage, it is impossible for me to tell which of the individual
projects the task names refer to.

Is there an easy way to identify the individual project tasks within
the different views? I'm working in Project 2003. (this is my first
posting, so I hope I'm making myself clear enough).