We use Ms Project 2003 Standard and have a just established a resource pool.
When I open the pool I get 3 options - if I choose the 3rd option, Project
creates a master file project with all the other linked projects inserted.
If I save this master project file and don't modify it by making changes
within it, will it be dynamically updated when changes are made to the linked
projects by other project managers?
Thanks
Mark