I
Ian Gray
Hi all,
I have been handed a Project 2002 file that will be used to run a global
project and asked to put in an update & control system. I am a planner who is
used to Primavera P3.
The plan was put together as one project initially, but after reading the
posts here and considering the breadth of the project (14 Stakeholders with
seperate but linked activities) and the fact that the stakeholders are
geographically seperated, I think Sub Projects will be the way to go.
My questions are:
1 - How do I separate the one file into the Master (Milestones etc) and the
14 separate Subs?
2 - Does anyone have suggestions / issues / ideas as to how the update
process can be completed? The subprojects will have to be emailed out to the
stakeholders, updated and then sent back. Unfortunately we are running Lotus
Notes (various versions) and so the Outlook integrattion will not be possible.
Help! ;-)
I have been handed a Project 2002 file that will be used to run a global
project and asked to put in an update & control system. I am a planner who is
used to Primavera P3.
The plan was put together as one project initially, but after reading the
posts here and considering the breadth of the project (14 Stakeholders with
seperate but linked activities) and the fact that the stakeholders are
geographically seperated, I think Sub Projects will be the way to go.
My questions are:
1 - How do I separate the one file into the Master (Milestones etc) and the
14 separate Subs?
2 - Does anyone have suggestions / issues / ideas as to how the update
process can be completed? The subprojects will have to be emailed out to the
stakeholders, updated and then sent back. Unfortunately we are running Lotus
Notes (various versions) and so the Outlook integrattion will not be possible.
Help! ;-)