J
John Cello
Apparently the density of my skull bone impairs me from figuring this out, so
i beg for help.
Putting together a project plan for training courses. In these courses, I
will use tests, which I have entered as material resources with a per use
cost. The problem I am running into is that when I assign these resources to
a task, the cost isn't adding up.
For example, one test has a cost of $20. If I assign that resource to a
task, with 20 units, the cost should calculate to be $400, right? But it sits
at $20 (or whatever the cost per use of that particular resource is.)
Please let me know what I'm doing wrong here.
Thanks in advance.
i beg for help.
Putting together a project plan for training courses. In these courses, I
will use tests, which I have entered as material resources with a per use
cost. The problem I am running into is that when I assign these resources to
a task, the cost isn't adding up.
For example, one test has a cost of $20. If I assign that resource to a
task, with 20 units, the cost should calculate to be $400, right? But it sits
at $20 (or whatever the cost per use of that particular resource is.)
Please let me know what I'm doing wrong here.
Thanks in advance.