C
Coen
Hi,
In my project large volumes of soil are processed by a contractor. This
contractor has made a projectplanning (2003) based on its demand. To get an
overview of the required amounts I have assigned material resources to the
contractors planning.
My job is to provide the contractor with the right amount and quality of
soil. My sources are other excavation projects that have their own schedules.
To get an overview of the future supply/demand and possible future
shortages, I have made a supply schedule in Excel and try to connect the
demand schedule by exporting the Work of the contractors' planning through
the "Analyze timescaled Data in Excel". This should work and gives me the
opportunity to present the difference (supply/demand) in graphs. Problem
however is that MSProject somehow divides all 'demand' quantities by 60 and
presents the volumes in hours.
Does anyone know how to export the right quantities to Excel (instead of
hours)? In the 'Resource graph' View, the right volumes (in cubic metres) are
presented....
Maybe there is a more effective way to connect the supply planning (my own
planning) to the contractors demand planning to get an instant overview of
future shortages etc. in MSProject?
In my project large volumes of soil are processed by a contractor. This
contractor has made a projectplanning (2003) based on its demand. To get an
overview of the required amounts I have assigned material resources to the
contractors planning.
My job is to provide the contractor with the right amount and quality of
soil. My sources are other excavation projects that have their own schedules.
To get an overview of the future supply/demand and possible future
shortages, I have made a supply schedule in Excel and try to connect the
demand schedule by exporting the Work of the contractors' planning through
the "Analyze timescaled Data in Excel". This should work and gives me the
opportunity to present the difference (supply/demand) in graphs. Problem
however is that MSProject somehow divides all 'demand' quantities by 60 and
presents the volumes in hours.
Does anyone know how to export the right quantities to Excel (instead of
hours)? In the 'Resource graph' View, the right volumes (in cubic metres) are
presented....
Maybe there is a more effective way to connect the supply planning (my own
planning) to the contractors demand planning to get an instant overview of
future shortages etc. in MSProject?