C
chris.read-smith
Can anyone help me.
I am currently using a EPM 2003 solution at work. I have created our
plans using an earned value based off the physical % complete, which
IS what I require in the industry I work in. My plan is broken down
into stages, each stage representing a different set of tasks that is
required to do the job. On a weekly basis, I imput 'actual hours'
into my project plans and track progress and slippage from this. I
create my own reports using different views in MSP to show PV, EV,
ACWP, SV, SV%, CV, CV%, BAC, EAC, VAC, CPI & SPI. I also run off
filtered views (As MSP's built in Reports are useless) showing tasks
that should have started and tasks that should have finished. I also
run off reports showing upcoming milestones in the next month as well
as any incomplete milestones that are not complete. I create my own
SPI and CPI graphs in excel to see the trend on a week by week state
as well as convert my PV & EV into hours and run a report on this
too. So, I run alot of reports that do work and do drive the plans in
the direction I need them to go. All up its about a 26 page report
cover about 8 different plans.
However, what I have found is this. In my plan, for example, a stage
may not be planned to commence for about a month. Infact, the stage
is complete. All the work is done on this, yet we have not had this
schedule to start for a month. (The workers had worked a bit longer
and got the job done). THe problem is, because the first task in this
stage isnt planned to have started, its SPI is taking the EV and
dividing it by 0 resulting in 0 as the SPI.
I feel that in a case like this, yes, you are ahead of schedule in
that stage yet because your PV is $0.00 you SPI doesnt reflect this.
(I do realise that when this status date finally reaches the stage
then the SPI will shoot through the roof) but for now, the SPI stays
at '0'. Stupid Project!!!!
This leads into my next question. Because this work was done ahead of
schedule. How do I get a resource view to show that less work is now
required for the time that, that work was meant to have been done.
Because, really, the standard 'Resource Graph's' in project.. The
peak units, the work and all the other views in 'Format >Details' dont
reflect this. Is there a view that you can see that recoginses that
this work has been done ahead of schedule and not as much work has to
be done now for that scheduled time?
Also, each week, I run a filter that shows, "Tasks that should have
finished and havent finished". This is a good view to have. Yet it
is only as good as a resource tool that can assist it. I have heard
Primavera can do what im trying to think of but what I need is, a
resouce graph that shows me, how many men I need to complete the
unfinished work. Or do you have to keep 'rescheduling this incomplete
work' in "Update Project", reschedule the work and then look at your
resource graph. If this is the only solution this has good points and
bad points. Good being, it will paint a true picture of the work that
is required by rescheduling any incomplete work ahead of the status
date yet bad as you dont want your workers to realise that you can
just reschedule your plans anytime you dont complete a job?
Any suggestions.
Many Thanks
Chris
I am currently using a EPM 2003 solution at work. I have created our
plans using an earned value based off the physical % complete, which
IS what I require in the industry I work in. My plan is broken down
into stages, each stage representing a different set of tasks that is
required to do the job. On a weekly basis, I imput 'actual hours'
into my project plans and track progress and slippage from this. I
create my own reports using different views in MSP to show PV, EV,
ACWP, SV, SV%, CV, CV%, BAC, EAC, VAC, CPI & SPI. I also run off
filtered views (As MSP's built in Reports are useless) showing tasks
that should have started and tasks that should have finished. I also
run off reports showing upcoming milestones in the next month as well
as any incomplete milestones that are not complete. I create my own
SPI and CPI graphs in excel to see the trend on a week by week state
as well as convert my PV & EV into hours and run a report on this
too. So, I run alot of reports that do work and do drive the plans in
the direction I need them to go. All up its about a 26 page report
cover about 8 different plans.
However, what I have found is this. In my plan, for example, a stage
may not be planned to commence for about a month. Infact, the stage
is complete. All the work is done on this, yet we have not had this
schedule to start for a month. (The workers had worked a bit longer
and got the job done). THe problem is, because the first task in this
stage isnt planned to have started, its SPI is taking the EV and
dividing it by 0 resulting in 0 as the SPI.
I feel that in a case like this, yes, you are ahead of schedule in
that stage yet because your PV is $0.00 you SPI doesnt reflect this.
(I do realise that when this status date finally reaches the stage
then the SPI will shoot through the roof) but for now, the SPI stays
at '0'. Stupid Project!!!!
This leads into my next question. Because this work was done ahead of
schedule. How do I get a resource view to show that less work is now
required for the time that, that work was meant to have been done.
Because, really, the standard 'Resource Graph's' in project.. The
peak units, the work and all the other views in 'Format >Details' dont
reflect this. Is there a view that you can see that recoginses that
this work has been done ahead of schedule and not as much work has to
be done now for that scheduled time?
Also, each week, I run a filter that shows, "Tasks that should have
finished and havent finished". This is a good view to have. Yet it
is only as good as a resource tool that can assist it. I have heard
Primavera can do what im trying to think of but what I need is, a
resouce graph that shows me, how many men I need to complete the
unfinished work. Or do you have to keep 'rescheduling this incomplete
work' in "Update Project", reschedule the work and then look at your
resource graph. If this is the only solution this has good points and
bad points. Good being, it will paint a true picture of the work that
is required by rescheduling any incomplete work ahead of the status
date yet bad as you dont want your workers to realise that you can
just reschedule your plans anytime you dont complete a job?
Any suggestions.
Many Thanks
Chris