L
Lelaina Pierce
I have a series of MS Project 2003 schedules that all calculate SPI.
I have linked entire schedules into a master summary schedule and the
SPI rolls up and calcualtes fine (I do this to report top-level SPI to
management.)
My issue is that I need to link an individual task (w/ SPI) from
within a schedule to my master summary schedule. I tried adding a
Predecossors task by pointing to the specific file and row I'm trying
to link from but when I do this, the SPI value does not come across.
How do I get SPI value from one schedule into another AND have that
value roll up into the top, summary SPI value?
I have linked entire schedules into a master summary schedule and the
SPI rolls up and calcualtes fine (I do this to report top-level SPI to
management.)
My issue is that I need to link an individual task (w/ SPI) from
within a schedule to my master summary schedule. I tried adding a
Predecossors task by pointing to the specific file and row I'm trying
to link from but when I do this, the SPI value does not come across.
How do I get SPI value from one schedule into another AND have that
value roll up into the top, summary SPI value?