P
prashanth.sharangapani
Dear Friends,
I have this scenario. I use MPP 2007.
I have a task that is complete, but the SPI shows 0.79. The task data
looks as below -
Task Name BCWS BCWP SPI
-----------------------------------------------------------------------------------------------------------------------------
Summary Task $14,337.48 $11,337.48 0.79
Task A $11,049.98 $8,049.98 0.73
Task B $2,587.50 $2,587.50 1.0
Task C $700.00 $700.00 1.0
All tasks are complete. How can Task A have this data? Is this because
I might have deleted some tasks under the 'Summary Task'?
How do I correct this?
Thanks,
Prashanth
I have this scenario. I use MPP 2007.
I have a task that is complete, but the SPI shows 0.79. The task data
looks as below -
Task Name BCWS BCWP SPI
-----------------------------------------------------------------------------------------------------------------------------
Summary Task $14,337.48 $11,337.48 0.79
Task A $11,049.98 $8,049.98 0.73
Task B $2,587.50 $2,587.50 1.0
Task C $700.00 $700.00 1.0
All tasks are complete. How can Task A have this data? Is this because
I might have deleted some tasks under the 'Summary Task'?
How do I correct this?
Thanks,
Prashanth