In project 2002 on the Resource Sheet, the Max. Units for a resource
would display the correct value for the Current Date. If a resouce
had different units for different available from/available to dates,
the displayed value would be the correct max units for the current
date. In project 2003 the displayed value appears to be the value the
last time the resource was changed in the enterprise pool. For
eaxmple, if on March 1st you set dates in the enterprise pool for a
resourfe to be:
from 3/1 to 5/31 units = 0
from 6/1 to NA units = 100
The max units for that resouce added to a plan on 6/6 would be 0 not
100 in project 2003 (it would be 100 in project 2002).
Is this a bug? Is there a fix for it?
would display the correct value for the Current Date. If a resouce
had different units for different available from/available to dates,
the displayed value would be the correct max units for the current
date. In project 2003 the displayed value appears to be the value the
last time the resource was changed in the enterprise pool. For
eaxmple, if on March 1st you set dates in the enterprise pool for a
resourfe to be:
from 3/1 to 5/31 units = 0
from 6/1 to NA units = 100
The max units for that resouce added to a plan on 6/6 would be 0 not
100 in project 2003 (it would be 100 in project 2002).
Is this a bug? Is there a fix for it?