Hi,
I'm studying MS Project in the above book (Microsoft Press, by Joli Ballew,
Deanna Reynolds, Bonnie Biafore). But I'm sometime afraid by what seems to
be strange errors.
Especially, page 367:
"When Project automatically levels resources, you want to be sure that any
conflicts that arise between the sharer file and the resource pool are
always resolved in the same way. Specifically, you want the resource pool to
always win any conflict. What setting do you need to enable to configure
this?
The answer cited as good is: Pool Takes Precedence.
What do you think of this assertion?
I'm quite confused. Is the 70-632 exam such tricky?
Thanks for your opinion.
Xiao
I'm studying MS Project in the above book (Microsoft Press, by Joli Ballew,
Deanna Reynolds, Bonnie Biafore). But I'm sometime afraid by what seems to
be strange errors.
Especially, page 367:
"When Project automatically levels resources, you want to be sure that any
conflicts that arise between the sharer file and the resource pool are
always resolved in the same way. Specifically, you want the resource pool to
always win any conflict. What setting do you need to enable to configure
this?
The answer cited as good is: Pool Takes Precedence.
What do you think of this assertion?
I'm quite confused. Is the 70-632 exam such tricky?
Thanks for your opinion.
Xiao