J
J Baird
Has anyone ever seen this merge error before, and if so, what data is in
"column 54"? (No, we don't have any views with 54 columns in them.)
Here's what produced this error:
1) Create a new schedule from a template (any template produced this for us,
so we know it's not the template)
2) Open a schedule file that's saved in Xml format (schedulename.xml)
3) Select the "Merge the data into the active project" option (in the Import
Wizard)
4) Click finish
Error message text:
An import error ocurred.
Check Row 1 Column 54
Enter an actual work value that is less than the total work on the
summary task
To continue importing with additional error messages, click Yes.
To continue importing with no error messages, click No.
To stop importing, click Cancel.
Obviously, [Acutal Work] is often less than [Work], unless the assignment is
100% complete. If the task is 100% complete, then the amounts are even. I
don't know if the error message is referring to a task, assignment or
resource. In MSP, I can't find any task, assignment or resource that has
[Actual Work] that is greater than "Total Work", or even equal to Total
Work, unless the task is 100% in both [Work complete] and [% Complete].
I know the XML spec pretty well, so I started looking at the XMl code, but I
can't figure this error out.
"column 54"? (No, we don't have any views with 54 columns in them.)
Here's what produced this error:
1) Create a new schedule from a template (any template produced this for us,
so we know it's not the template)
2) Open a schedule file that's saved in Xml format (schedulename.xml)
3) Select the "Merge the data into the active project" option (in the Import
Wizard)
4) Click finish
Error message text:
An import error ocurred.
Check Row 1 Column 54
Enter an actual work value that is less than the total work on the
summary task
To continue importing with additional error messages, click Yes.
To continue importing with no error messages, click No.
To stop importing, click Cancel.
Obviously, [Acutal Work] is often less than [Work], unless the assignment is
100% complete. If the task is 100% complete, then the amounts are even. I
don't know if the error message is referring to a task, assignment or
resource. In MSP, I can't find any task, assignment or resource that has
[Actual Work] that is greater than "Total Work", or even equal to Total
Work, unless the task is 100% in both [Work complete] and [% Complete].
I know the XML spec pretty well, so I started looking at the XMl code, but I
can't figure this error out.