G
Gerjan
When i create a cash flow-report (Visual Report) in Project 2007 (Dutch
version) the week numbers and the days of the week in the cash flow report
are not the same as in MS Project.
Sample:
I created a new project with 1 task:
- duration 15 days;
- start: Mon 23-02-09;
- end: Fri 13-03-09.
I added 1 resources to the task (costs € 50,00/hour; 8 hours/day)
I created a Cash-flow report (Report --> Visual Reports --> Cash
Flow-report) and set the level of the content to days.
MS Projects created a Pivot Table in Microsoft Excel. When I expand the
pivot table to weeks and then to days my result is:
Week Days Costs
07 23 400
07 24 400
07 25 400
08 26 400
08 27 400
08 28 0
08 01 0
08 02 400
08 03 400
08 04 400
09 05 400
09 06 400
09 07 0
09 08 0
09 09 400
09 10 400
09 11 400
10 12 400
10 13 400
It should be: week numbers 9, 10 and 11 Mo - Fr 400 en Sa - Su 0.
Is this a bug in Microsoft Project 2007 or can I change a setting?
version) the week numbers and the days of the week in the cash flow report
are not the same as in MS Project.
Sample:
I created a new project with 1 task:
- duration 15 days;
- start: Mon 23-02-09;
- end: Fri 13-03-09.
I added 1 resources to the task (costs € 50,00/hour; 8 hours/day)
I created a Cash-flow report (Report --> Visual Reports --> Cash
Flow-report) and set the level of the content to days.
MS Projects created a Pivot Table in Microsoft Excel. When I expand the
pivot table to weeks and then to days my result is:
Week Days Costs
07 23 400
07 24 400
07 25 400
08 26 400
08 27 400
08 28 0
08 01 0
08 02 400
08 03 400
08 04 400
09 05 400
09 06 400
09 07 0
09 08 0
09 09 400
09 10 400
09 11 400
10 12 400
10 13 400
It should be: week numbers 9, 10 and 11 Mo - Fr 400 en Sa - Su 0.
Is this a bug in Microsoft Project 2007 or can I change a setting?