Microsoft Project server 2002 web access colors

A

Ashish Hosalkar

Hi,
There hours in the MS Project 2002 Web Access "View
Resource Assignments" are shown in different colours.Could
somebody please let me know what these colours indicate.
Regards
Ashish
 
J

Jonathan

Goto Admin -> Customize PWA -> gantt Chart format,

you can see the definition of colors and symbol over there.
 
D

Dale Howard

Ashish --

Red numbers indicate Actual Work hours that have been entered by the team
member, but have not been updated into the project plan by the project
manager. Black numbers indicator Actual Work that has been updated into the
project plan by the project manager. Hope this helps.

--
Dale A. Howard
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 
G

Guest

Thanks, Dale..
That is helpful..There are blue numbers too.
Could you please let me know what they indicate.
Regards
Ashish
 