Microsoft Project Server - Actual Work Protected vs Work

E

Eric

Hi, let's say that I have a schedule with a task that has a "Work" value of
100 hours.

My employee logs 150 hours on this task, and I approve it.

Will this task show 100 hours, or 150 hours in the Actual Work field in the
"Task Usage" view?

Thank you.
Eric
 
G

Gérard Ducouret

Hello Eric,

Definitely, this task will show 150 hours of Actual Work in Project Pro.

Gérard Ducouret
 
D

Dale Howard [MVP]

Eric --

In the future, please post your Project Server questions in the
microsoft.public.project.server newsgroup, as this newsgroup is dedicated to
the Microsoft Project desktop application only. To answer your question,
you will see 150 hours in the Actual Work field in the Task Usage view.
Remember that in Microsoft Project, Actual Work always replaces planned
Work. The only way to see the original planned Work on the task is to view
the Baseline Work for the task, assuming you saved a Baseline for your
project, of course. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top