Value of Work (Scheduled Performance Indicator (SPI)). Basically the
difference between Cumulative Work (BCWS) and the Earned Value of Worked
Accomplished (BCWP). It's a number which informs us if a contract is on the
projected schedule.
I already have the program calculating BCWP. I need the BCWS (the projected
cumulative hours to date) to complete the formula.
Already tried. They don't calculate to the values I need. This corporation
doese EVMS reporting a little different. Most of the values I had to
manually formulate.