KL said:
what are advantages of displaying the schedule as a network versus a gantt
chart

It's all in the eyes of the viewer. Take a look at both and see which
you prefer. Some like one vs. the other.
 
S

Steve House

The Gantt chart focuses on task timing, the Network Diagram focuses on task
relationships and process. If you disregard summary tasks, the Network
Diagram is a flowchart that describes the logical process that produces the
project's deliverables.
 