We migrated to a new Dell Platform of servers and I am having difficulties
getting the OLAP cube setup on the new configuration. I have followed the
Microsoft Project Server 2003 Install guide and used the common sense
approach on what looks logical, but cannot get it to work.



Can you provide help or assistance?
 
G

Gary L. Chefetz [MVP]

Determined:

You need to say something more than it's not working. Please try to describe
your issue, the steps you're taking and the feedback the system is giving
you.
 