M
Marcus Pierce
I'm in the process of migrating our firm from 2002 to 2003 (enterprise). We
are setting up an entirely new server (physical and all). We have
successfully migrated the entire 2002 database onto the new
server--everything went swimmingly and it seems to be an exact copy (1000's
of resources, all kinds of codes, settings, permissions, etc.). However, we
would now like to make some configuration/customization changes to the new
server before we go live with it. The problem is that, right before we go
live (at which time we are also deploying the 2003 client enterprise-wide),
we will need to import the latest projects plans, since changes will have
been made to them in the meantime. Is there a way to import just the plans
without overriding all of our new customizations? There are about 50 plans,
some quite large.
Thanks,
--Marcus
are setting up an entirely new server (physical and all). We have
successfully migrated the entire 2002 database onto the new
server--everything went swimmingly and it seems to be an exact copy (1000's
of resources, all kinds of codes, settings, permissions, etc.). However, we
would now like to make some configuration/customization changes to the new
server before we go live with it. The problem is that, right before we go
live (at which time we are also deploying the 2003 client enterprise-wide),
we will need to import the latest projects plans, since changes will have
been made to them in the meantime. Is there a way to import just the plans
without overriding all of our new customizations? There are about 50 plans,
some quite large.
Thanks,
--Marcus