T
Tom Zehrbach
Question 1: Is there a way to create a new Task from an existing Issue? If
not, is there a way to import Tasks from a spreadsheet into an EXISTING
project? (Export a bulk list of Issues to a spreadsheet, then import them
into an existing Project).
Question 2: I've set the "Specify the default method for reporting progress
on tasks" to "Hours of work done per day...". However, when attempting to
report hours worked on a task, the reporting "style" remains at "Percent of
work complete...".
Question 2a. I'm assuming that by setting the default method of
reporting above, that this sets the default method for all projects. Is
there a way to specify the reporting type on a per-project basis?
Question 3: Is there any way to set up automatic notification to a resource
when an issue has been assigned to that resource (I realize this is a
Sharepoint question, but someone here might know it)? I know that resources
can create an alert for the issue list, I'm looking for a little more
elegant solution.
not, is there a way to import Tasks from a spreadsheet into an EXISTING
project? (Export a bulk list of Issues to a spreadsheet, then import them
into an existing Project).
Question 2: I've set the "Specify the default method for reporting progress
on tasks" to "Hours of work done per day...". However, when attempting to
report hours worked on a task, the reporting "style" remains at "Percent of
work complete...".
Question 2a. I'm assuming that by setting the default method of
reporting above, that this sets the default method for all projects. Is
there a way to specify the reporting type on a per-project basis?
Question 3: Is there any way to set up automatic notification to a resource
when an issue has been assigned to that resource (I realize this is a
Sharepoint question, but someone here might know it)? I know that resources
can create an alert for the issue list, I'm looking for a little more
elegant solution.