Jean Malenfant
Hello All !
In the normal course of my work, I produce document.
Milestone 1 in my Schedule.
These documents are approved by my customer/partner. They
typically have 10 days to approve the document. MileStone
2.
I want to reflect this second milestone in my MSProject,
but I dont want to create a task of 10 Days representing
my customer work, because I dont control that external
ressource, nor do I pay it so it is not a cost to the
project.
In the other hand my future development cannot start
before I received the Approval (milestone 2).
Is there a trick that I can use to make a milestone
dependent of another one with an offset in time... Or any
other thing that do the Job.. I am easy ;-)
Tks to all
J.
In the normal course of my work, I produce document.
Milestone 1 in my Schedule.
These documents are approved by my customer/partner. They
typically have 10 days to approve the document. MileStone
2.
I want to reflect this second milestone in my MSProject,
but I dont want to create a task of 10 Days representing
my customer work, because I dont control that external
ressource, nor do I pay it so it is not a cost to the
project.
In the other hand my future development cannot start
before I received the Approval (milestone 2).
Is there a trick that I can use to make a milestone
dependent of another one with an offset in time... Or any
other thing that do the Job.. I am easy ;-)
Tks to all
J.