Milestone relative to another Milestone

J

Jean Malenfant

Hello All !

In the normal course of my work, I produce document.
Milestone 1 in my Schedule.

These documents are approved by my customer/partner. They
typically have 10 days to approve the document. MileStone
2.

I want to reflect this second milestone in my MSProject,
but I dont want to create a task of 10 Days representing
my customer work, because I dont control that external
ressource, nor do I pay it so it is not a cost to the
project.

In the other hand my future development cannot start
before I received the Approval (milestone 2).

Is there a trick that I can use to make a milestone
dependent of another one with an offset in time... Or any
other thing that do the Job.. I am easy ;-)

Tks to all

J.
 
S

Sarah

Jean,

Simply link Milestone 1 FS + 10 days to Milestone 2. This means that
Milestone 2 is scheduled to start 10 days after Milestone 1 finishes.

Sarah
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top