Relative Timelines

Joined
Sep 30, 2013
Messages
1
Reaction score
0
I'm repeating a question that I found on the forum, I don't think it was answered, but it's my question too:

Any suggestions how to create a relative timeline?
For instance, an event begins on day 0, the first milestone occurs 6 days
later (day 6), the next one 2 weeks later (day 20) etc.

We want to use this for a recurring project - for example, a job requires a quarter of a year to do, has a number of milestones in it, but one instance of it could start at one point, other instances at other points.

We'd like to enter the starting point, for example 10/1/2013, and have the milestones calculated based on relative distance (in days) from that point. For example, the first milestone might be due in two weeks. In this case, 10/15. But another task based on this model may start 10/8 so, after setting that as the start date, we'd like the due date to show as two weeks later, in this case, 10/22.

Is this feasible? If so, can you point out where I'd set this option?

Thanks,
Don
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top