milestone values randomly changing?

J

jay

MS Project Server 2003 SP-1

After applying task changes to a project (click the Update button, the
project opens and the changes are applied), Milestone values may RANDOMLY
change (from 'Yes' to 'No' or from 'No' to 'Yes') at either the detail task
level or summary task level. User reproduced this occurrence this a.m. in my
presence...one detail task's Milestone value went from 'Yes' to 'No'.
....odd, very odd... Same user had previously reported this oddity. So,
every week, when the user applies task changes (to approx. 6 projects), the
user must evaluate (and re-assign) any of the randomly changed Milestone
values for each project and then re-save.

This has not been reported by any other users in our installation (70+
published server projects).

Advice on this matter is greatly appreciated. Thank you.
 
J

jay

Yes, this is the case - resources are assigned to the milesone and reporting
actuals...thanks Gary!
 