Good Morning:

I'm still testing this environment and found that if I put
a milestone in my project plan in project pro 2003 with a
0 duration, 0 work that when I publish to the server and
later try to update that as complete by entering 100% in
either the % complete or % work complete it reverts back
to 0% when I synch with the server.

Also when I try to update it via PWA by entering 0
remaining work, nothing happens.

Is there a fix/ work around, or do I need to create a
bogus user account for "milestones" to assign a small
value of work to in order to update this?

Thank you in advance for your help.

Ryan
 