Milestones from Multiple Projects

J

J Fenbert

We have a set of files that each contain 3-5 key
milestones. We would like to develop a view that combines
the milestones from all the files into a single Gantt
chart. In Project 2000 we would build a master file and
filter for those tasks. Is there a better way to do that
with Project 2003?

thanks.
 
D

Dale Howard [MVP]

J Fenbert --

Create a master project in Project 2003 and apply the Milestones filter to
the master project. If you want to save your master project in the Project
Server database, you will need to ask your Project Server administrator to
set the "Allow master projects to be saved to Microsoft Project Server"
feature to Allow on the Server Configuration page in PWA. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 

Ask a Question