I am having a slight struggle with some of my project managers who are
creating plans.
I don't like seeing Milestones with its predessesor the summary bar to which
it belongs and I know it's considered bad MSP practise. However people
persist in doing this.
What is a good argument I can use to explain this should not be done? Why
shouldn't this be done?
Meljay