Hi - i am trying to do something very simple!! - i would like to show a
milestone in a summary bar.
the summary consists of 5 linked tasks the 3rd is a milestone. I have
selected the summary line and gone to Project/Task Information/General tab.
and checked the "show rolled up Gantt bars" I did the same for the ID the
milestone is on - nothing has changed - i then thought if i changed the bar
style for the milestone to include "rolled up" that would help but this just
hid the milestone from inside the task.

what have i done wrong
 
M

Matthew Hodgson

Hi there.

If you double click on the task name and go to the general tab, there is a
selection box to check, "roll up Gantt bar to summary". Check this is
selected too.

There are other ways to force milestones to appear at the summary level. You
can include flag fields in the bar styles definition and calculate the flag
results based on a formula to automate the process.

Hope this helps,

Matthew
 
A

andy

Hi matthew,
I have tried the freindly way still no luck - how do I force it and what
formulae can i use

Sorry for the lack of knowledge
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top