Hi !

I have a problem in MS-project, I have a masterplan in MS-project that
contains several other MS-project plans and they have a whole bunch of
activities and some milestones here comes the problem, when i set the
milestone tasks to be rolled up to the main subproject bar for each
subproject i get a milestone symbol at the main sub project bar but the
name does not show up, what should i do to get the name rolled up to ?

Best regards Kjell A
 
M

Michael.Tarnowski

Hi !

I have a problem in MS-project, I have a masterplan in MS-project that
contains several other MS-project plans and they have a whole bunch of
activities and some milestones here comes the problem, when i set the
milestone tasks to be rolled up to the main subproject bar for each
subproject i get a milestone symbol at the main sub project bar but the
name does not show up, what should i do to get the name rolled up to ?

Best regards Kjell A

--
Kjell Andersson
------------------------------------------------------------------------
Kjell Andersson's Profile:http://forums.techarena.in/members/195747.htm
View this thread:http://forums.techarena.in/microsoft-project/1316505.htm

http://forums.techarena.in

Hi KJell

have a look at
http://www.screencast.com/users/Bil...es/media/e6019aeb-d0a1-4c3f-9993-a695e4f5bdd9

HTH
Cheers, have a nice day
Michael
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top