Hi,
i've deployed a project server 2003 with SQL Server 2000. Here is the
problem:
1)- using Project professional 2003, i add new resources to a project
by Enterprise Resource Pool,
2)- these resources i can't find them when adding new RISKS or ISSUES,
at 'Assigned To' i can't find my resources else 'administrator' and
'projserv' where:
* administrator is the Project Server administrator,
* projserv is the MS SharePoint administrator.

i thought that it is a security permission issue, anybody help.
Any suggestions will be appreciated.
Thanks a lot.
 
R

Ray McCoppin

I think they need to be assigned to a task before they will be added to the
WSS site and thus to the pick list. I think you also need to publish the
project.

Hope this helps.
 
G

Gary L. Chefetz [MVP]

Ray's previous reply to you is "on the money." What else are you looking
for?
 
G

Gary L. Chefetz [MVP]

You need to assign resources to a task and publish their assignment before
you can assign risks and issues to project team members.
 
A

Abobakr Nasr

HI, Gary

After some experiments, i find out that only 'Windows Accounts' could
be appeared in the 'Assigned To' dropdown list in 'New Risk' page or
'New Risk' page and 'Local Account' couldn't be dispalyed. So, is the
problem in MS SharePoint or in Enterprise Resource Pool and what is the
resolution?
Thanks.
 
G

Gary L. Chefetz [MVP]

Abobakr:

By design. You must have a Windows account to use SharePoint.
 
A

Abobakr Nasr

Gary,

i almost find out that by experiment, but isn't there any back door to
handle this problem or not?
Thanks for your time.
Thanks again.
 
G

Gary L. Chefetz [MVP]

The backdoor is to not use SharePoint, or manually change everything to
allow anonymous access.
 