Missing Tasks from Tasks View

S

Sam

We have project server with SP1 implemented . For one of our resource when he
submits time against a task and then the task update is accepted and updated
by the Proj manager. From then on that resource is unable to see that task on
the Tasks View. Even though we checked the PM can see that task is still
assigned to that resource in the Project Plan. Even republishing the plan
doesnt make the task show up in resource timesheet.
The Resource can not now assign himself to that task again since Project
server thinks task is already asigned to the resource so it does not show the
task in the list of " Assign myself to an existing task ". Can anybody
suggest how to fix this ? Any changes directly to DB for this resource etc?
 
D

Dale Howard [MVP]

Sam --

If the team member completed the task and has the Current Tasks option
selected, then the system will hide that task on the View My Tasks page.
Does this describe your situation? Let us know.
 
S

Sam

The Task is not complete yet for e.g. for a 20 hr task only 4 hrs were
entered. Also All Tasks option is selected . Strange thing is this problem
has been reported by only 1 specific resource. I personally also dont see
that problem.
 
S

Sam

Just found the solution to this issue . The Resource having this problem was
Proposed in the Template and the Projects in which he was having this issue .
Changing from Proposed to Commited and republish fixed the issue.
 