Modify resource calendars with non-working times.

C

C. Smith

We would like to modify the resource calendars with non-working times. I
tried to enter a vacation on a resource's calendar and got a message that all
calendars were locked. This is really an important function to be able to
show impacts of vacations.
Any insight?
 
R

Reid McTaggart

Did you open the Enterprise Resource Pool before trying to modify the
resource's calendar? Enterprise resources have to be "checked out" before
their personal calendars can be modified.
 