Modifying MS Office Project 2003 Pro reports to show ACTUAL WORK.

I

Ivor Davies

Can someone provide some insight on how to view ACTUAL WORK in the canned
reports with MS Office Project Professional?

All the existing reports show WORK (NOT ACTUAL WORK) - we need to be able to
report on what work is actually being done (not estimated for each task
within each project).

I have tried to play with some of the reports, but they are not producing
the desired results.

Can someone help?

For example - what table do we use? (I tried using the ENTRY and ENTRY- WORK
RESOURCES tables).

Please help...

Thanks..

Ivor
 
D

Dale Howard [MVP]

Ivor --

Here's an example of how to change the Who Does What When Report to show
Actual Work instead of Work:

1. Click View - Reports
2. Double-click the Custom section
3. Select the Who Does What When report and then click the Copy button
4. Rename the new Report to something like "Who Does What When - Actual
Work"
5. Change the Work field to the Actual Work
6. Click the OK button
7. Click the Preview button

Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com


"We wrote the book on Project Server"
 
I

Ivor Davies

Thanks Dale for your assistance!

As always you are there when we need help or just a point in the right
direction.

Take Care..

Ivor
 
Top