P
Peter Rooney
Hope this isn't a daft question...
I have a programme plan - that is a Microsoft Project plan that contains
lots of sub
projects.
It was created by my predecessor and was (I presume) scheduled by Start Date.
I want to change one or more of the sub projects so that I specify an end
date for
the last task, and it works backwards to tell me the latest date I can start
the project to achieve the desired end date (as it would if I'd specified
"scheduled by Finish Date" when the plan was created).
I only want certain parts of the plan to behave in this way, however.
Is this possible?
Will this question generate more weary head shaking than my tiny ego can
handle?
Pete Rooney
I have a programme plan - that is a Microsoft Project plan that contains
lots of sub
projects.
It was created by my predecessor and was (I presume) scheduled by Start Date.
I want to change one or more of the sub projects so that I specify an end
date for
the last task, and it works backwards to tell me the latest date I can start
the project to achieve the desired end date (as it would if I'd specified
"scheduled by Finish Date" when the plan was created).
I only want certain parts of the plan to behave in this way, however.
Is this possible?
Will this question generate more weary head shaking than my tiny ego can
handle?
Pete Rooney