Modifying PWA Resource Assignment View in Project Server 2003

R

robin.woody1

Can anyone tell me if there is a way to modify the resource assignment
view in Project Web Access 2003? The view shows the tasks by resource,
but does not display the task's summary task. However, from the task
view, the summary task is displayed. Is there a way to change this?

Also, from PWA, we want to allows users to change the start date of an
assigned task but cannot find a configuration for this. Any
suggestions?

Thanks!
 
J

Jonathan Sofer

To your second question. Per project, you can go to
Tools>Customize>Published Fields and add the Actual Start to the fields
available in Task View. You can then set the field to show as the assigmnet
date and enable the resource to edit this date. You can then add this field
to the timesheet view and they will be able to edit it for that project.

But also, just by putting in their first actuals on a certain date, won't
that set the actual start date and wouldn't you get the same result?

Jonathan
 
Top