Monthly view only

B

Benjiluck

Hi is it possible to display month only timescales in both gantt and calendar
views. I want to be able to view long lists of tasks by month along the
timeline, is this possible?

thanks for any help you can give

B
 
R

Rod Gill

The calendar view is daily only. You can show months in the Gantt Chart by
changing the timescale.
 