Move all dates forward by 2 weeks

J

Junada0

Project 2007 - Date move question.

First post on this forum, would appreciate any help

RE: Project move - all tasks

Is there a simple method to move all dates in a project plan forward b
a given number of days, say 1 week, 1 month etc.

So that *all* the dates move forward or indeed backwards if required.

Many thank
 
J

JulieS

Hello Junada0,

If you need to move the start date of an entire project, choose Project
Project Information and supply a new start date to the project. If
the tasks are appropriately linked (predecessor and successor
relationships set) and have not been constrained, then all the tasks
should move without trouble.

If you have set constraints other than ASAP and need to move constrained
tasks, show the Analysis toolbar and click the "Adjust Dates" button.
The button will adjust all tasks relative to the initial start date.
I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
Top