Hi,
I have about 11 tasks in my schedule that are slipping.
I have two types of slipping tasks:
1) Tasks were supposed to start last week but have not even started
2) Tasks were started last week but are not completed (were due to finish
10/16/Fri).
I am trying to bring these tasks current or future date.
What I have done:
1) From the menu: Tools >> Tracking >> Update Project
2) Click on the "Reschedule uncompleted work to start after: 10/18/09
3) Which brought those slipping tasks current however, now all these tasks
have Start No Earlier Than (SNET) task type constraint.
4) Leveled the schedule.
5) This (obviously) pushes the phase end date out about 1.5 weeks and there
is no buffer room in the schedule for such delay (need to finish the phase by
12/15/09 - we are down to the cruch time here), so you can his concern about
filling in every possible gap in the schedule as possible.
My Question:
My Proj. Mgr thinks that the SNET task type constraint will put a some sort
of grid lock on the those tasks and this will not allow the leveling engine
to work effectively. He wants me to figure out a way to move past/incomplete
tasks to current date & retain ASAP task type constraint.
I proposed to create a dummy buffer task called "Milestone for slipped task"
& set it to 10/19/09 then put this task as predecessor to all these 11
slipped tasks & he thinks that this is putting artificial logic and doesn't
like that idea either.
Does anyone have any suggestion for me on how to move past incomplete tasks
to current date without altering the original task type (ASAP) constraint?
Appreciate your input and time!!!
Best,
Lilly
I have about 11 tasks in my schedule that are slipping.
I have two types of slipping tasks:
1) Tasks were supposed to start last week but have not even started
2) Tasks were started last week but are not completed (were due to finish
10/16/Fri).
I am trying to bring these tasks current or future date.
What I have done:
1) From the menu: Tools >> Tracking >> Update Project
2) Click on the "Reschedule uncompleted work to start after: 10/18/09
3) Which brought those slipping tasks current however, now all these tasks
have Start No Earlier Than (SNET) task type constraint.
4) Leveled the schedule.
5) This (obviously) pushes the phase end date out about 1.5 weeks and there
is no buffer room in the schedule for such delay (need to finish the phase by
12/15/09 - we are down to the cruch time here), so you can his concern about
filling in every possible gap in the schedule as possible.
My Question:
My Proj. Mgr thinks that the SNET task type constraint will put a some sort
of grid lock on the those tasks and this will not allow the leveling engine
to work effectively. He wants me to figure out a way to move past/incomplete
tasks to current date & retain ASAP task type constraint.
I proposed to create a dummy buffer task called "Milestone for slipped task"
& set it to 10/19/09 then put this task as predecessor to all these 11
slipped tasks & he thinks that this is putting artificial logic and doesn't
like that idea either.
Does anyone have any suggestion for me on how to move past incomplete tasks
to current date without altering the original task type (ASAP) constraint?
Appreciate your input and time!!!