Move Project Server to new hardware

J

Jeff

I need to move our MS Project server to new physical hardware. Can anyone
tell me hwat is involved in this? I am assuming it basically means
reinstalling the app on the new server and then restoring the database. Is
there anything else that is involved?

Thanks.


Jeff
 
S

Sean

Jeff:

Take a look at the MSFT documentation. You need to prepare for this. If you’re planning on restoring, you’ll need to restore both the Proj Server DB as well as the WSS DB. Restoring both to the same point in time is crucial. MSFT documentation on this is actually quite good.

http://go.microsoft.com/fwlink/?LinkID=20234

Hope this helps!
 