Hi The Weather is Nice,
You are welcome for the assistance so far and thanks for the feedback.
Well, you've stumped me with the further explanation. [Not too hard to do

] Your explanation is clear, I just can't fathom how sorting the
project file would accomplish what I believe you are looking for which is a
filtered lists of tasks showing just a specific resource but without any
summary tasks showing.
I do panic mildly when someone suggests renumbering the task IDs (the
permanently renumber option). In testing, removing the check from the "keep
outline structure" had no effect on the display of summary tasks. The only
thing I can come up with is the field sorted by was forcing the summary
tasks to sort to the bottom of the sorted list and, in a large project file,
they were out of view.
Do let us know if the custom filter option I suggested or if Mike's
suggestion for a quick macro to turn summary tasks off and on works to your
liking, if not, we'll try again.
Julie
PS: I just have to ask -- exactly *where* is the weather nice?