C
Chris
I can duplicate my problem by performing this simple
scenario.
Two embedded subprojects projects, inserted into an empty
master, one subproject with 1 task and the other with 2.
All start As Soon As Possible. Nothing fancy, just what
the default template provides.
The only task of the first subproject is the predecessor
of the first task ot the second. The first task of the
second is the predecessor of the second task. This second
task has a deadline.
Whenever the deadline is exceeded , rather than getting
the expected Red symbol I am getting a Conflict pop up
window.
Any suggestions?
Chris
scenario.
Two embedded subprojects projects, inserted into an empty
master, one subproject with 1 task and the other with 2.
All start As Soon As Possible. Nothing fancy, just what
the default template provides.
The only task of the first subproject is the predecessor
of the first task ot the second. The first task of the
second is the predecessor of the second task. This second
task has a deadline.
Whenever the deadline is exceeded , rather than getting
the expected Red symbol I am getting a Conflict pop up
window.
Any suggestions?
Chris