In creating a new project, I want the first task line to be a zero number. I
have seen projects done that way but when I try to set one up, the first line
is always 1.
 
J

Jan De Messemaeker

Hi Andree,

The first line will ALWAYS have 1 as ID.
However, go to Tools, Options, View, and check on
Show Project Summary task
That will cretae the 0 line you must have seen.
HTH

Jan - Project MVP





"Andree" <[email protected]
t.com> wrote in message
news:[email protected]...
 
A

Andree

Thanks Jan, you're an angel!!

Jan De Messemaeker said:
Hi Andree,

The first line will ALWAYS have 1 as ID.
However, go to Tools, Options, View, and check on
Show Project Summary task
That will cretae the 0 line you must have seen.
HTH

Jan - Project MVP





"Andree" <[email protected]
t.com> wrote in message
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top