I am working on a project with 2 different callendars assigned to resources
one is 24 Hours when I use a resource withthis calendar assigned it shows
correct on the time and the Gant chart.
Second resource callendar is set up for work days at 24 hours except SEP
2009 is 10 hr days sundays non working when I assign a task to this callendar
it shows incorrec days and the Gant shows working straight through. Help
 
J

JulieS

Hi Ray,

You really can't get an accurate view of when work is occuring
through the Gantt chart view. Try looking at the Task Usage view to
ensure that you are seeing the correct amount of work per day on the
correct days.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 