MS Project 2007 Summary Task Bar won't move

J

John Mc

Hi All
After an office colleague used my PC to make a plan on MS Projects 2007 he
seems to have messed my settings up, grrrr
Now when I move any tasks within a group, the Summary Task Bar doesn't
automatically move to the new 'start' and 'end' dates.
Now I can move all the sub tasks to another day, yet the Summary bar just
stays where it was.
Where is the setting to automatically have Projects re-evaluate the Summary
Bar.

Regards
John
 
J

Jan De Messemaeker

Hi,

Tools, Options, Calculation, set to Automatic.

If it still doesn't work your file has really been messed up.
Then delete links to and from summary asks till it works.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
J

John Mc

Hi Jan

Thank you very much for the very fast response,
the Automatic Calculation was the missing link,
seems my boss had set it to Manual ....
Lesson learned here .... never let your boss play on your PC !!

Thanks again
John
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top