Hi All
After an office colleague used my PC to make a plan on MS Projects 2007 he
seems to have messed my settings up, grrrr
Now when I move any tasks within a group, the Summary Task Bar doesn't
automatically move to the new 'start' and 'end' dates.
Now I can move all the sub tasks to another day, yet the Summary bar just
stays where it was.
Where is the setting to automatically have Projects re-evaluate the Summary
Bar.
Regards
John