Thanks for the response. Actually, my situation is more like having 8
painters for a huge number of painting jobs. I can assign any painter
to
any
task (because they are equally qualified to paint). However, there are
1000
painting jobs of varying work, so I want to optimally assign these
painters
to the jobs so that I complete all the jobs as quickly as possible (and
therefore get paid as soon as possible).
I'm understanding a lot more about the use of MS Project, and I just
don't
think it can do what I want it to. I'll keep my ears open for any
other
input.
Thanks.
:
All of your resources work on all of the tasks in the project????
This
is
highly unusual in that in most environments the various members of the
group
of resources have different qualifications, skills, and specialties.
The
carpenter cannot do the work of the plumber who in turn cannot do the
work
of the electrician. Likewise each task in the project also has unique
skill-sets required - painting the walls requires the skills of a
painter,
not those of a plumber, while installing the pipes requires skills
that
only
the plumber posseses. Therefore when you assign resources you cannot
put
both the painter, the carpenter, the electrician, and the plumber as a
group
on all of the tasks regardless of the nature of the work and let
leveling
sort out who does what, but that is what it sounded like you're doing.
Leveling does not ever assign resources, add them to or take them off
of
tasks. All it ever does is delay work. If you assign a group of
resources
to a task a task and some of them are over-allocated because they're
also
assigned to other tasks at the same time, when you resource level one
of
two
things will happen (depending on the setting in the leveling options).
One
possibility is that the task is delayed in toto, all the work shifted
until
such time as all the over-allocated resources are clear of their
conflicts.
The other possibility is the work for the non-overallocated resources
remains on the days it was originally scheduled while the work for the
over-allocated resources is delayed, leading to an apparent
lengthening
of
the task (it takes longer to do all the work but the total amount of
work
remains constant).
Hope this helps clarify it.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
It sounds like I don't know what leveling is for. I use MS Project
to
help
me schedule the work for all tasks in a project. I do this by
entering
the
tasks and the work required for each t ask. I then assign all of my
available resources to each task and use the leveling feature to
allow
MS
Project to assign the resources as required to the tasks. This lets
me
figure out what the end date of the project is.
My guess, based on the response, is that this is not a valid thing
to
do.
However, a month after I performed the above entry, one of the
employees
(that was now assigned to a number of tasks) turned in his
resignation.
How
do I get him removed from all of his assignments? Do I have to go
through
every task and remove him manually? Why can I not just tell MS
Project
that
he is unavailable on his resignation date? Is there some tutorial
on
how
MS
project does leveling, taking into account availability dates?
Thanks.
:
Hi Brett,
Please note that this would mean a new product since the principle
of
your
question implies a completely new approach to leveling: now it
NEVER
changes
assignment units, not for temporary workforce but neither for any
other
circumstance.
HTH
--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs:
http://www.mvps.org/project/faqs.htm
"Brett" <
[email protected]> schreef in bericht
After allocating all resources for the project and allow
microsoft
to
allocate evenly over all tasks, an employee submits his/her
resignation.
It
would be nice if MS Project would allow the changing of the
Resource
Availability dates to reflect this fact and then allow for
releveling
to
parcel the work to the other resources in the group. However,
when
currently
doing this, MS Project comes up with overallocations for the
resource
that
left.
----------------
This post is a suggestion for Microsoft, and Microsoft responds
to
the
suggestions with the most votes. To vote for this suggestion,
click
the
"I
Agree" button in the message pane. If you do not see the button,
follow
this
link to open the suggestion in the Microsoft Web-based Newsreader
and
then
click "I Agree" in the message pane.
http://www.microsoft.com/office/community/en-us/default.mspx?mid=16631352-17
f9-4ed4-ad26-620af5a8d094&dg=microsoft.public.project