D
Dave
Will project show critcal path without real constraints in place? If you
have linked two tasks and assigned the first with the constraint of finished
no earler than June 30 and the second task as start no sooner than June 30,
there is no constraint and no critical task/path.
If the above second task had a constraint of start no latter than June 28,
then there would be a critical task and it would show red and a critical path
would also show.
So, it is possible to set up a project with no critical path by using the
correct combination of constraints... YES/NO ???
have linked two tasks and assigned the first with the constraint of finished
no earler than June 30 and the second task as start no sooner than June 30,
there is no constraint and no critical task/path.
If the above second task had a constraint of start no latter than June 28,
then there would be a critical task and it would show red and a critical path
would also show.
So, it is possible to set up a project with no critical path by using the
correct combination of constraints... YES/NO ???