Dasani
Using MS Project Server 2003 we require team members to report actuals
(hrs worked) per day AND remaining work (hrs) left for the task. Is
there anyway to do so? I only see 3 options for forcing managers to
comply and that is not an option.
Also we require team members to report to a manager who will then
approve/reject updates then get updated in the plan. Overall project
manager (1 person) will review and republish then print variance
reports against baseline values. Any advice on how to configure? Any
advice on how to hide columns from PWA to restrict team members what
they see?
Thanks
(hrs worked) per day AND remaining work (hrs) left for the task. Is
there anyway to do so? I only see 3 options for forcing managers to
comply and that is not an option.
Also we require team members to report to a manager who will then
approve/reject updates then get updated in the plan. Overall project
manager (1 person) will review and republish then print variance
reports against baseline values. Any advice on how to configure? Any
advice on how to hide columns from PWA to restrict team members what
they see?