We would like to create a view that would summarize key milestones from
different projects into one view or report, so that we could see potential
conflicts of deliverables coninciding on the same or nearby dates dates. We
have not been able to create this within MSP Web Access.

Do you have any suggestions?

We are using MSP Server and MSP Web Access 2003.
 
G

Gary L. Chefetz [MVP]

PWA does not give you the ability to aggregate task-level data across
projects. You can do this using the Project Client. You can accomplish
something similar using external links in a milestone plan that you can
display in PWA. Another approach is to extend the cube to include task data
or use SQL reporting services.
 