MSP won't assign certain days for a resource

V

Vic

Hi,

I have a resource that MSP will NOT assign a certain week's worth of work
for these tasks. There are no predecessors to the tasks and his Work
Calendar is clear.

When I try to force those the resource to work those days (via the Resource
Sheet) by entering the hours in the "Work" Row, it enters the amount in the
"Actual Work" row as well.

Any thoughts as to why it refuses to schedule these days for this resource?
 
L

Lívia

HI,
I had seen this problem earlier. Delete the resource, and the task, and add
both again, and it will work. I hope :)
 
D

Dave

Vic said:
Hi,

I have a resource that MSP will NOT assign a certain week's worth of work
for these tasks. There are no predecessors to the tasks and his Work
Calendar is clear.

When I try to force those the resource to work those days (via the Resource
Sheet) by entering the hours in the "Work" Row, it enters the amount in the
"Actual Work" row as well.

Any thoughts as to why it refuses to schedule these days for this resource?

Is it for specific tasks or all of them?

Is there any actual work in the future with respect to the date for
which you want to schedule work?

Is there any pattern to the days for which it won't schedule the work?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top