F
Frederick
Good day,
Looking for help in order to "activate" the display of a year (i.e. 2006) in
the Portfolio Analyzer year dimension.
We have project plans going into 2006, yet the OLAP cube does not seem to be
"picking up" data from these, or possibly I only need to configured PWA to
allow the year to be displayed. Currently, the year 2006 is not displayed and
therefore cannot be selected from the "pick list dropdowns" of the portfolio
analyzer. Would appreciate any help to get this configured ASAP, thanks!!
Looking for help in order to "activate" the display of a year (i.e. 2006) in
the Portfolio Analyzer year dimension.
We have project plans going into 2006, yet the OLAP cube does not seem to be
"picking up" data from these, or possibly I only need to configured PWA to
allow the year to be displayed. Currently, the year 2006 is not displayed and
therefore cannot be selected from the "pick list dropdowns" of the portfolio
analyzer. Would appreciate any help to get this configured ASAP, thanks!!